Construction of the E117 international road section Kvesheti-Kobi highway (road section)

About Project

Within the framework of the Kvesheti-Kobi road project, the construction of 12.7 km long, two-lane asphalt-concrete road, 5 bridges and 4 tunnels, as well as the rehabilitation of 1 bridge is planned. The dimensions of the tunnels are1541 m, 194 m, 388 m and 299 m.

The total length of the bridges is 1.6 km. One of them will be a 426 m long and 166 m high arched bridge, which is the most difficult engineering construction. The length of its arch is 285 meters and, at this stage, it has no analogues in Georgia. The project also envisages the construction of 435 m long and relatively small (322 m, 218 m, 148 m and 42 m) bridges.

In addition to the main road infrastructure components, the project includes setting up a visitor center. This facility will serve as a potential center for agribusiness, conservation, ecotourism development and community sustainable development in the project area. The visitor center is a part of the project and it will directly benefit the local population of Khadi valley.

The construction of the Kvesheti-Kobi tunnel started in 2020 and will be completed in 2025.

პროექტის შესახებ
Employment
Employment

455 people are employed on the construction of the Kvesheti-Kobi tunnel, including 249 Georgian citizens.

Construction company
Construction company

The construction works of the project are carried out by the international company China Railway 23rd Bureau Group Co., Ltd.

Funding
Funding

The project is funded by the donor organization Asian Development Bank (ADB) and its budget is 316.7 million GEL.

Monitoring

The construction process is supervised by the international company UBM ULUSLARARASI BİRLEŞMİŞ MÜŞAVİRLER MÜŞAVİRLİK HİZMETLERİ A.Ş. The supervisory team at the site checks the conformity of the construction materials and performance of the works, conducts the necessary laboratory tests, quality control, checks the compliance of labor and safety during the course of the works, agrees on the construction work methodologies, checks the execution of the work schedules, the volumes of the works performed, studies environmental and social issues. It also prepares monthly reports and approves technical documentation (drawings, engineering reports).